印尼芝拉扎三期工程百万机组“体检”合格
Indonesia Cilacap III Project's Million-Unit "Health Check" Passed
2019年11月8日,由国网湖北电科院负责调试的印尼芝拉扎三期工程百万机组一次性通过168小时满负荷试运行,正式投入商业运行。该工程位于印度尼西亚中爪哇省芝拉扎县,装机容量为1×100万千瓦,全部使用中国电站设备和技术标准,是中国出口的首批百万级火电机组之一,也是共建“一带一路”倡议落地印尼的重要项目。
On November 8, 2019, the one-million-kilowatt generating unit of Indonesia's Cilacap III Project, commissioned by the State Grid Hubei Electric Power Research Institute, successfully completed its 168-hour full-load trial operation in a single attempt and was officially put into commercial operation. Located in Cilacap County, Central Java Province, Indonesia, the project has an installed capacity of 1×1 million kilowatts, fully adopting Chinese power equipment and technical standards. It is one of the first million-kilowatt coal-fired power units exported by China and a significant BRI project implemented in Indonesia.
出品|中央广播电视总台国际在线 国务院国资委宣传局、新闻中心
特别鸣谢|国网湖北省电力有限公司