To ensure a reliable power supply during the winter peak and safeguard the operation of the railway trunk line, State Grid Jiangxi EHV Company seized the low-traffic window between 3:00 and 6:00 a.m. on November 12. The company tested tethered drone emergency lighting equipment and completed the nighttime replacement and upgrading of the ground wire on the 500-kV Fengfu Line at its crossing over the Shanghai-Kunming Railway.
To minimize the impact on normal railway operations, State Grid Jiangxi EHV Company coordinated extensively with railway authorities in advance, carefully scheduled the nighttime construction window, and prepared a dedicated construction plan. The company innovatively adopted the "zero-protection-angle netting method for double-circuit conductors" to overcome technical challenges, minimized the duration of high-risk operations above the railway, and firmly safeguarded the safety of both the power grid and the railway. (By Li Yanan)